CONNECTICUT DEPARTMENT OF TRANSPORTATION
NEWS RELEASE
2800 BERLIN TURNPIKE P.O. BOX 317546
NEWINGTON CONNECTICUT, 06131-7546 |
FOR RELEASE: April 11, 2014 |
FOR FURTHER INFORMATION:
OFFICE OF COMMUNICATIONS
TELEPHONE: (860) 594-3062
FAX: (860) 594-3065
WEB SITE: www.ct.gov/dot |
Replacement of the highway signing will consist of removing existing overhead, side mounted and post mounted signs and installing new overhead, side mounted and post mounted signs on existing sign supports and new sign supports. Ramp signing will also be included for removal and replacement. Work will begin on May 1, 2014.
DOT Project No. 0172-0387 was awarded to AM Rizzo Electrical Contractors, Inc. at a cost of $3,216,000 on December 6, 2013, and is scheduled to be completed on November 22, 2015.
LANE CLOSURE INFO
Lane closures are allowable south of Exit 14 during the following time periods:
Northbound - Monday thru Friday from 8:00 p.m. to 6:00 a.m., Friday thru Sunday from 11:00 p.m. to 9:00 a.m., and Sunday from 11:00 p.m. to 6:00 a.m. Monday
Southbound - Monday thru Friday from 7:00 p.m. to 6:00 a.m., Friday thru Sunday from 8:00 p.m. to 8:00 a.m., and Sunday from 7:00 p.m. to 6:00 a.m. Monday
Lane closures are allowable north of Exit 14 during the following time periods:
Northbound - Monday thru Friday from 7:00 p.m. to 12:00 p.m., Friday thru Sunday from 8:00 p.m. to 2:00 p.m., and Sunday from 10:00 p.m. to 12:00 p.m. Monday
Southbound - Monday thru Friday from 7:00 p.m. to 6:00 a.m., Friday thru Sunday 8:00 p.m. to 10:00 a.m., and Sunday from 6:00 p.m. to 6:00 a.m. Monday